Woolwich Dockyard, Boosting Water

Woolwich Dockyard

Boosting Water

Installed boosted water sets with break tanks to 3 blocks 

Woolwich Dockyard

Woolwich House, Plant Room

Woolwich Dockyard

Plant Room

Renewal of aging district heating system supplying 332 properties.

Installation of 6 boiler rooms.

Installation of distribution pipe work.

Owen Waters House

Owen Waters House, Ilford

Plant Room

Installation of new plant room.

5 pipe distribution pipe work.

Internal rad circuits within 88 properties over the two blocks.

Use of Aquatherm plastic welded pipe.

Wordsworth House

Wordsworth House, Greenwich

Plant Room

Installation of roof top 805KW plant room.

Use of temporary boilers and pumps to provide minimum disruption to the 120 properties.